LANDOWNER

  1. Works with engineer/consultant to develop a  tide gate design that meets all agency requirements and landowner goals, including fish passage approval, water management plan development, and acceptable inundation levels.
  2. Works with engineer/consultant and TGC to prepare permit applications and associated documents.

TIDE GATE COORDINATOR*

  1. Assists landowner in the coordination of permit consultation, tide gate design, and preparing information sufficient to apply for project permits

AGENCIES

  1. Respond to landowner questions, if requested.

STEP 5  OUTCOMES

• Tide gate engineering design sufficient to submit for permit approval.
• Permit applications and associated documents prepared with sufficient information to submit for review and approval.